Dinah sitting on the flatwork form, helping chisel out a path for the water spout plumbing.

The rough concrete after we pulled the plywood formwork off.

This was the form-work for the runnel that we pre-cast and then placed on the cast-in-place concrete portion of the fuente shown below.

Just finished the concrete skimcoating and ready for the runnel.

With the runnel was installed and the paint/waterproofing almost finished.

With the terra cotta spout installed and the plants in the bog garden in the back.

Off and running.